Weekly Upgrade Updates by Woodard and Curran


2019.07.29 Status Report

October 28, 2019



PAYMENT PROGRESS
Original Construction Cost$23,823,759.00
Total Approved Change Order Cost (1-5)$827,895.70
New Construction Cost$24,651,654.70
Total Payments Approved to Date (1-15)$14,413,762.72
Total Paid to Date (Pay Request No 1 - 14)$12,978,095.52
Percent of Project Complete (Billed)62%

As of November 20, 2019

Disclaimer

You are now leaving the Town of Enfield website. Links to external websites do not constitute endorsement by the Town of Enfield of the linked websites or the opinions, information, products or services contained therein. When you link to new websites you will be subject to the privacy policies of those sites. The Town of Enfield does not control the privacy policies of other websites and assumes no responsibility or liability for the actions of other website providers, including, but not limited to their use of your information.